Page 101 - SAMENA Trends - November-December 2021
P. 101

REGULATORY & POLICY UPDATES  SAMENA TRENDS

        Ofcom and BT Adopt Changes to Help 10Mbps Broadband USO


        Ofcom  has  finalized  the  changes  that  were  first  confirmed  in  July
        to improve how BT handles  delivery of the UK’s Universal Service
        Obligation (USO), which aims to bring faster broadband ISP speeds
        to those who can’t yet receive a 10Mbps+ capable download speed
        and aren’t planned to do so in the near future. We’ve already covered
        this topic and the changes extensively before (summary), so on this
        occasion we’ll just cut right to the chase. In short, some of those who
        applied to request a USO connection from BT have faced a number
        of problems with  poor communication,  unreliable cost quotes
        and others were also asked to pay materially higher amounts than
        they  should  have been  (e.g.  some of those who initially  requested
        the  USO were footing  a big  chunk of the  bill for everybody  else).
        Back  in  May  2021  BT  revealed  that  they’d  moved to  improve their
        processes  and communication.  Furthermore,  they also introduced
        a  new  cost  sharing “option” for their USO  quotes  (here), which
        enabled  communities to  “crowdfund and share  the excess cost of
        a broadband network upgrade “(preferable to lumping all the costs
        on to the first accepted quotes / homes). In addition, if more than
        70% of premises in a cluster register their interest, a contribution of
        an “additional £3,400 per premise” was included, thus lowering the
        excess costs that a community might have to pay (it’s very tricky to
        get this kind of thing right). On top of that, the 4G solution that BT
        shipped in response to most other USO requests was upgraded to
        include unlimited data (some people can also get an external antenna
        installed, if necessary). Ofcom’s proposals in July largely put what
        BT had already done – to improve how the costs of USO connections
        are calculated  and  or shared  between  properties – into  the  rules.
        But it also made a few other clarifications and changes too, which
        have today been formally adopted. The  regulator  recognized that
        BT had agreed to change its approach for quotes where the cost of
        connecting a property is not significantly above the £3,400 threshold.   number  of customers receiving  lower quotes  in the future.
        BT also agreed to refund affected customers and re-issue quotes it   Meanwhile, the Government’s £5bn Project Gigabit program
        has previously provided. Crucially, this won’t solve all of the much   has  similarly  warned  that  those  in  the  final  0.3%  would  be
        more complicated underlying problems with areas that are simply far   prohibitively expensive to reach (here) and they’re consulting
        too expensive to resolve via the USO (e.g. some people have been   on how to solve this (we expect new wireless networks and
        quoted hundreds of thousands, even millions of pounds). At a certain   LEO satellites to be options). On the other hand, BT may find
        point, the value for money side goes well out of the window and keeps   the new approach to be quite challenging. Likewise, there is a
        on running. Like it or not, the cost of deploying Fiber-to-the-Premises   risk that the new approach to shared costs could cause some
        (FTTP) infrastructure into some extremely remote rural areas can be   confusion for those who apply for the USO after the fiber has
        insane, which is an unavoidable reality. Such barriers cannot easily   been run down a street or lane, following the first customer
        be swept aside by good intentions or small tweaks. Indeed, in some   request (i.e; some of those who apply later might not realize
        cases it would literally be cheaper to build somebody a new house,   that they still have to pay their share of the  USO  cost  for
        in a better connected area, than to run a new fiber line. Nevertheless,   delivery, which could be hefty).
        the changes that BT and Ofcom have made should still result in a



        T-Mobile Netherlands Loses Appeal Against KPN Copper Switch-Off Schedule


        T-Mobile Netherlands has lost a  court   postpone  national PSTN operator  KPN’s   it announced in February 2020. T-Mobile,
        appeal against rival KPN’s planned copper   plans to switch off copper lines and migrate   while in the process of rolling out its own
        network shutdown  schedule,  and says  it   services to fiber-optics, arguing that it will   fiber  infrastructure,  relies  on  wholesale
        will  now argue  its  case to the regulator,   not have adequate time to transfer its own   access to KPN’s network for wide internet
        the Authority for Consumers and Markets   customers. KPN  aims  to  decommission   coverage, and the company has requested
        (ACM).  In  late September  T-Mobile   copper  network  services  at more than   a two-year delay in the copper switch-off
        launched  a  court  case in an  attempt to   two million addresses in Q1 2023, a plan   process.
                                                                                                    101  NOV-DEC 2021
   96   97   98   99   100   101   102   103   104   105   106